Single Critical Task Crashing Case

Compare incremental crash cost with indirect cost saved for one critical activity.

Projects workspace● Runs in your browser
01 Your input
02 Your result
View or copy raw result data
FormulaCost per day cut = (v.crash_cost-v.normal_cost)/(v.normal_days-v.crash_days) ; Net saving = v.days_to_cut*(v.indirect_daily-(v.crash_cost-v.normal_cost)/(v.normal_days-v.crash_days))
Sources and model references

Worked example

Inputs

Normal days
10 days
Crash days
6 days
Normal cost
10000 currency
Crash cost
16000 currency
Days to cut
3 days
Indirect daily
2000 currency/day

Expected results

Cost per day cut
1500 currency/day
Net saving
1500 currency

Load the example in the workspace to reproduce these results. Display rounding does not change the underlying calculation.

How to use this tool

  1. Enter your own assumptions using a consistent currency and period.
  2. Review the scenario outputs and compare alternative inputs.
  3. Check the stated model limits before using the result in an operating plan.

Try this example

{
  "normal_days": 10,
  "crash_days": 6,
  "normal_cost": 10000,
  "crash_cost": 16000,
  "days_to_cut": 3,
  "indirect_daily": 2000
}

Accuracy and scope

Assumes this task stays on the sole critical path and cost slope is linear. Does not recompute a network or parallel critical paths.