Project Forecast Cost to Complete

Forecast final cost at current cost efficiency and assess the remaining-budget efficiency requirement.

Projects workspace● Runs in your browser
01 Your input
02 Your result
View or copy raw result data
FormulaForecast total = v.budget*v.actual/v.earned ; Forecast remaining = v.budget*v.actual/v.earned-v.actual ; Required efficiency = (v.budget-v.earned)/(v.budget-v.actual)
Sources and model references

Worked example

Inputs

Budget
100000 currency
Earned
40000 currency
Actual
50000 currency

Expected results

Forecast total
125000 currency
Forecast remaining
75000 currency
Required efficiency
1.2 ratio

Load the example in the workspace to reproduce these results. Display rounding does not change the underlying calculation.

How to use this tool

  1. Enter your own assumptions using a consistent currency and period.
  2. Review the scenario outputs and compare alternative inputs.
  3. Check the stated model limits before using the result in an operating plan.

Try this example

{
  "budget": 100000,
  "earned": 40000,
  "actual": 50000
}

Accuracy and scope

Deterministic planning scenario; inputs are assumptions, not forecasts. Excludes taxes, financing, legal requirements and costs not explicitly entered. Source explains the underlying planning framework; this specific scenario arithmetic is original.