Project Delay Economic Impact

Combine extended overhead with foregone benefits and explicit contractual cost assumptions.

Projects workspace● Runs in your browser
01 Your input
02 Your result
View or copy raw result data
FormulaExtended overhead = v.delay*v.overhead_day ; Lost benefit = v.delay*v.benefit_day ; Total impact = v.delay*(v.overhead_day+v.benefit_day)+Math.min(v.delay*v.penalty_day,v.penalty_cap)
Sources and model references

Worked example

Inputs

Delay
20 days
Overhead day
500 currency/day
Benefit day
800 currency/day
Penalty day
100 currency/day
Penalty cap
1500 currency

Expected results

Extended overhead
10000 currency
Lost benefit
16000 currency
Total impact
27500 currency

Load the example in the workspace to reproduce these results. Display rounding does not change the underlying calculation.

How to use this tool

  1. Enter your own assumptions using a consistent currency and period.
  2. Review the scenario outputs and compare alternative inputs.
  3. Check the stated model limits before using the result in an operating plan.

Try this example

{
  "delay": 20,
  "overhead_day": 500,
  "benefit_day": 800,
  "penalty_day": 100,
  "penalty_cap": 1500
}

Accuracy and scope

User-supplied contractual cost assumptions; does not determine enforceability, liability or whether delayed benefits are permanently lost.

Is my data uploaded?

This tool runs locally in your browser. Input and output are not sent to a processing server. Copy or download your result before leaving the page.