Earned Value Project Health

Assess cost and schedule performance from planned value, earned value and actual cost.

Projects workspace● Runs in your browser
01 Your input
02 Your result
View or copy raw result data
FormulaCost variance = v.earned-v.actual ; Schedule variance = v.earned-v.planned ; Cost index = v.earned/v.actual ; Schedule index = v.earned/v.planned
Sources and model references

Worked example

Inputs

Planned
50000 currency
Earned
45000 currency
Actual
48000 currency

Expected results

Cost variance
-3000 currency
Schedule variance
-5000 currency
Cost index
0.9375 ratio
Schedule index
0.9 ratio

Load the example in the workspace to reproduce these results. Display rounding does not change the underlying calculation.

How to use this tool

  1. Enter your own assumptions using a consistent currency and period.
  2. Review the scenario outputs and compare alternative inputs.
  3. Check the stated model limits before using the result in an operating plan.

Try this example

{
  "planned": 50000,
  "earned": 45000,
  "actual": 48000
}

Accuracy and scope

Deterministic planning scenario; inputs are assumptions, not forecasts. Excludes taxes, financing, legal requirements and costs not explicitly entered. Source explains the underlying planning framework; this specific scenario arithmetic is original.

Is my data uploaded?

This tool runs locally in your browser. Input and output are not sent to a processing server. Copy or download your result before leaving the page.