FormulaAverage hours = v.first_hours*Math.pow(v.units,Math.log(v.learning/100)/Math.log(2)) ; Total hours = v.first_hours*Math.pow(v.units,1+Math.log(v.learning/100)/Math.log(2)) ; Labor budget = v.first_hours*Math.pow(v.units,1+Math.log(v.learning/100)/Math.log(2))*v.hourly
Sources and model references

Worked example

Inputs

First hours
100 hours
Units
8 items
Learning
80 %
Hourly
30 currency/hour

Expected results

Average hours
51.2 hours/item
Total hours
409.6 hours
Labor budget
12288 currency

Load the example in the workspace to reproduce these results. Display rounding does not change the underlying calculation.

How to use this tool

  1. Enter your own assumptions using a consistent currency and period.
  2. Review the scenario outputs and compare alternative inputs.
  3. Check the stated model limits before using the result in an operating plan.

Try this example

{
  "first_hours": 100,
  "units": 8,
  "learning": 80,
  "hourly": 30
}

Accuracy and scope

Cumulative-average learning model: average effort falls by the supplied factor each doubling. Not an individual-unit curve or empirical forecast; assumes stable repetition.

Is my data uploaded?

This tool runs locally in your browser. Input and output are not sent to a processing server. Copy or download your result before leaving the page.